Baihetan Dam: concrete casting starts at the world's first million-kilowatt turbine generator

 

 

Concrete casting began at the world's first million-kilowatt unit spiral case on the left bank of Baihetan Hydropower Station on May 4, marking another solid step towards the goal of scheduled generation of the world’s second-largest hydropower station.

 

There were many kinds of pre-embedded parts in spiral case concrete, making the process of pouring a challenging task as it needed to keep dense at one corner while also preventing the volute from lifting.

 

Baihetan project team has set up a 24-hour duty squad on May 1, to ensure the smooth pouring of the first silo volute concrete. After 37 consecutive hours of hard work, the first silo volute concrete pouring successfully completed on May 5 as scheduled.

 
Home About Us Newsroom Data & Publications Featured Events & Proprams Power Industry Basics Contact Us
 
CEC in Brief
President鈥檚
Message
Executives
Functions
Structure
Members
CEC News
Industry News
Reports and Publications
Data/Statistics
Standards
Reliability
Events
Programs
Multimedia
Generation
Distribution/Grids
Consumption
Sustainability
Regulator
 
Copyright CEC All Rights Reserved.         No.1 Lane 2, Baiguang Road, Xicheng District, Beijing, 100761 China         E-mail:cecintl@cec.org.cn